MahaREAT Orders Mumbai Developer to Pay 2% Penalty and Share Sale Proceeds

The Maharashtra Real Estate Appellate Tribunal, known as MahaREAT has told the promoters of RA Residences in Dadar East to pay a penalty of 2 percent of the project cost. The promoters must also execute a conveyance deed, in favour of the housing society.

MahaREAT has ordered the promoters to give the sale proceeds from units, which were built using extra FSI and TDR beyond the 2017 plan to all the allottees. The promoters must also demarcate the remaining 64 guest parking spaces. Hand them over to the society.

The dispute began when the society said that the promoters used FSI without permission changed the approved plan and encroached on common areas and parking spaces. The 2017 plan was largely. Approved in 2021 and the commercial building area was increased a lot.

MahaREAT said that big changes needed prior informed consent from the allottees. MahaREAT also said that conveyance cannot be delayed forever once the building is finished the occupation certificate is obtained possession is handed over and the society is registered.

The tribunal added that any extra FSI or TDR that appears after the disclosed development potential has been used up cannot be used for construction once the obligation to convey the property has come into force.